What makes the price move
Three things decide whether the job fits in a half day or calls for a trench. None of them can be guessed over the phone.
A garage attached to the panel is a half day. A detached garage at the back of the lot means a trench, a conduit and a separate feed.
If it has to be upgraded to 200 amps, that becomes two jobs instead of one, with a request to file with the utility.
An unfinished basement goes quickly. A finished concrete wall, much less so. Closing the finish back up is part of the calculation.
Two vehicles charging the same night is not the same circuit. A second charger or shared charging gets decided before the work, not after.

We do not post prices and we do not give them over the phone. Two neighbouring houses can call for two very different jobs. We assess on site, then we quote.